Central Java 2000MW Power Plant

Central Java Power Project (Jawa Tengah), also known as PLTU Batang or Batang power station, is developed by the Independent Power Provider PT Bhimasena Power Indonesia (BPI). The project is located in Pemalang, Batang, in Central Java, Indonesia. Mitsui Engineering & Shipbuilding (MES) has been awarded the contract for the design and construction of the civil scope of works for the project including soil improvement and earthworks, piling works, foundations, a jetty as well as a 240m height chimney. Tebeton assists MES with the management and overall supervision of the civil scope of works for the project.

The boilers, turbines and generators are supplied by MHPS including the steel structures in which the equipment will be accommodated. Tebeton has been engaged by MHPS to supervise the off-site steel fabricators.

  • Location: Batang, Indonesia
  • Duration: February 2017 – present